CONSTRUCTION FEATURES
|
|
Date Construction Authorized | March 10, 1947 |
Date of First Main Line Weld | January 16, 1948 |
Date of Final Main Line Weld | September 25, 1950 |
Date of First Tankers Loaded at Sidon | December 2, 1950 |
Total Tonnage of Main Line Pipe | 265,000 Short Tons |
Total Tonnage of Steel | 325,000 Short Tons |
Total Ocean Freight Hauled | Approximately 3 billion ton-miles |
Total Freight Hauled Overland in Zone of Operations | Approximately 150 million ton-miles |
Construction Manpower in Zone of Operations | |
Americans Nationals | 1,557 |
Total Man-Months | 36,600173,000 |
Peak Number of Men | 14,559 |
Construction Equipment: | More than 3,000 large units, including 400 big Kenworth and International trucks. |
Total Number Engineering Drawings: | Approximately 2,000 |
Total Number Material Requisitions: | Approximately 7,000 |